|
One
day a
manager had an idea. The
manager thought that this new system would not be difficult to build,
after all
, it was simple idea and had obvious benefits. At least, he thought the
idea
was simple and the benefits were obvious to him. And the new system
couldn't
cost that much. Could it? His consultants and his vendors all thought
it was a
good idea. After all, it could mean work and money for them, so it must
be a
good idea. And
the
team knew that it was important that the cost was low and the time to
build was
short. It was important because otherwise the business case might not
get approved. Not
only
that, but it didn’t deliver what the business needed. The
manager was very
upset with the failure. He just couldn’t understand what the
problems were. His
project manager had consistently promised that the project was on time
and on
track. And he would know, wouldn't he? Unfortunately,
when it came to testing the system, it just didn’t work
properly. It didn’t do
what the users wanted, it was slow and the cost of the technology was
many
times that predicted in the business case. Suddenly, the project
manager's
promised deadlines failed. Previously all his estimates and deadlines
were met,
now, when it came to testing, that changed. The project manager had
claimed
that the project was 90% finished. Now it looked as though the last 10%
would take
as long as the first 90%. In
the
end the system was abandoned and the technical team were all
reprimanded. Some
lost their jobs. After all, they hadn’t delivered what the
business case
promised. When
the
project was independently reviewed it was discovered that the business
case had
drastically underestimated how long and how much the system would take
to
build. The conclusion was that the requirements kept changing, the
scope was
unclear and there was no technical leadership across the project. The
moral
to this story is: Bernard
Robertson-Dunn, June 2010 |
Home Parables |